Timber home entrance with a steep charcoal roof, granite steps, bronze-framed windows and autumn maple foliage.

Scranton Village in Woodstock CT: Plans and Permit Limits

October 29, 2026

"Basically like an old Main Street in America that used to be, that is not there anymore." That is how Josh Biando described Scranton Village to CT Insider this month. Biando writes children's books and designs amusement parks. The village he plans to build at 292 Route 169 in Woodstock will have a restored carousel at its center.

On paper, that is the most theatrical project Woodstock's stretch of Route 169 has seen in years. In the town's approval it reads very differently. Woodstock's Planning and Zoning Commission signed off on October 1 with a set of conditions. The site goes dark half an hour after closing, amplified music is banned, and the plans call for a red barn with a black roof. The village has to close by 9 p.m. on any night of the week.

A Set Designer Moves In Beside an Antique Barn

The village grows out of Scranton's Shops, which has been selling antiques on Route 169 for more than 30 years. CTvisit describes 3,800 square feet on two floors with more than 85 dealers. They sell furniture, primitives, pottery and collectibles, and admission is free. The same listing gives the shop's hours as Wednesday through Sunday, 11 a.m. to 5 p.m.

Biando brings a very different resume to that old barn. CT Insider reports that he lives in Oxford, Massachusetts, where his holiday displays are well known. His company, Big City Engineering, does movie set design, and he told the paper he has worked with Disney. His book "Polar & Finn: Christmas Chaos" is about two dogs, and they will give their names to the ice cream shop.

"I knew there was something special here," Biando wrote on Facebook, as quoted by CT Insider. "I walked the grounds multiple times, looking beyond what was already there and imagining what it could become."

What the Lot Is Supposed to Hold

The plan changed over the summer. In July, The Connecticut Scoop described the proposal as six shops, a café, an old-fashioned ice cream parlor, a general store, a carousel and a family train ride. The Scoop's October update after the vote lists eight small shops and makes no mention of a train.

Here is where each piece stood as of this month's reporting:

Element Where it stands
Scranton's antique shop Open
Gold mining experience Open
Polar & Finn's Ice Cream Shop and General Store Planned for one of the two existing buildings
Café Planned for the other existing building
Eight new small shops, about 400 square feet each Approved, no construction date
Restored 1951 Allan Herschell "Little Beauty" carousel Planned as the village centerpiece
Restaurant Biando told CT Insider he is talking with a potential tenant
Halloween and Christmas displays Listed in the village plans

The storefront size is the detail that sets this project apart. At roughly 400 square feet, each shop is about a tenth the size of the antique barn. Biando told CT Insider the small footprint is deliberate, "so smaller businesses can survive without the increased costs of rentals and electricity and all that. That's why we're creating a village." He also said the frozen treats will be named for characters from his books.

The Clock the Permit Set

Most of what will shape life around the village is in the approved permit, more than in the renderings. The October 1 minutes record maximum operating hours and the conditions attached to the vote. The commission approved it unanimously on a motion by Joseph Adiletta. The minutes note they had not yet been formally approved by the commission.

  1. Hours. The village can open no earlier than 9 a.m. It must close by 9 p.m. Monday through Saturday and by 5 p.m. on Sunday.
  2. Lights. All site lighting other than emergency lighting goes off 30 minutes after closing and can come on no sooner than 30 minutes before opening. That puts the lot dark by 9:30 p.m. at the latest on weekdays and Saturdays, and by 5:30 p.m. on Sundays.
  3. Fixtures. The applicant added a dark-sky compliant lighting plan before the vote.
  4. Sound. No amplified music on site.
  5. Tenants. Every shop lessee inside the village must follow the special permit's terms.
  6. Stormwater. A $5,900 bond for erosion and sediment controls, to be increased to also cover infiltration trenches and rain gardens, in an amount acceptable to the town planner.

Taken together, those conditions turn a designer's attraction into a daytime business. Holiday lights at a project like this tend to be the main draw. Here they will run on the same schedule as the parking lot fixtures, unless the town changes the permit. The 9 p.m. ceiling is also the latest hour on the permit. It is not a promise of how late the shops will actually stay open.

Why a Red Steel Building Belongs on Route 169

The building conditions make more sense once you look at the road. Route 169 is a federally designated National Scenic Byway, running 32.1 miles from Rocky Hollow Road in Lisbon to the Massachusetts line in Woodstock.

The byway's 2016 to 2026 corridor management plan describes the businesses along it as mostly small-scale: restaurants, specialty retailers, antique shops and agricultural businesses that "tend to draw little traffic." Among its recommendations are "signs and lighting that may protect the aesthetics and character of a village," and building types and site layouts "compatible with the traditional development of rural villages."

Scranton Village's final plans read like a response to those recommendations. Norm Thibeault of Killingly Engineering Associates walked the commission through the updates on October 1:

  • The 30-by-40-foot building will be steel, painted red with a black roof, "aligning to the agricultural theme of Woodstock."
  • The applicant provided examples of shed styles with porches that match the Scranton Village concept.
  • At the fire marshal's request, all buildings will sit 10 feet apart.
  • CT DOT has approved the plans.
  • Town Planner John Guszkowski noted that wetlands officials had been consulted and that the revisions have less impact than the original plan.

A carousel ringed by small sheds next to a red barn fits the byway's idea of a rural village. It just happens to have been designed by someone who builds movie sets.

The Questions From Across the Road

The project went through hearings over the summer. The town minutes show the application was presented on June 18 and sent to a public hearing on July 16. The hearing continued into September 17 and closed on October 1.

At the final session, about fifteen members of the public attended. Neighbors across Route 169 asked how traffic would move through the lot and where the new driveway would land. Thibeault walked through the traffic flow and the "do not enter" signs. He said the driveway would sit about 40 feet from a neighboring one. Another resident urged the commission to cap noise levels in the permit. The approval went further than a cap and banned amplified music outright.

The lighting conditions, the music ban and the hour limits all bear on the people who live along this stretch of road, not on the tourists the village hopes to draw.

What Isn't on a Calendar Yet

Neither the October news coverage nor the approval minutes give a construction start or an opening date for the new shops, the café, the ice cream counter or the carousel. The Connecticut Scoop's October update told readers to follow Scranton's Shops on social media for construction news. It also said prospective tenants interested in the new spaces can contact the business directly.

The holiday plans have the most room to grow. Biando told CT Insider he is working with the town on family-friendly Halloween and Christmas displays at the Woodstock fairgrounds. There, he said, he would have the space "to take everything I have created over the years to an entirely new level." The article gave no dates, hours or event details for a fairgrounds display, so for now it reads as a plan in discussion.

For now, the antique shop and the gold mining experience are the parts of Scranton's you can visit, on the stretch of Route 169 where the carousel is supposed to go.

Woodstock is home base for our team, so we pay attention to what gets approved along Route 169, from what goes up to how long the lights stay on. If you would like to talk through how a project like Scranton Village fits into your part of town, Jennie Kesselman and the Marquee Team are close by. Let's Connect.

Follow Us On Instagram